    1 Introduction
    This plan covers the content and enablement portions of the EPF 1.0 project. A separate plan covers the tooling
    component.
 
    2 Project Organization
    See also: http://www.eclipse.org/epf/
 The work is divided into a number of content areas. Each content area is lead by a committer that is the content lead,
    working closely with a number of committers and contributors. The content lead is responsible for making sure that bugs
    and enhancement requests are triaged and assigned, and responsible for updating the project burndown (status) on a
    weekly basis.
 
 We also have a content architect (Ricardo Balduino), who is responsible for the overall structure and integration of
    content from all content areas.
 
    The work is divided into the following content areas:
 
    
        Project management: Chris Armstrong (lead), Jochen Krebs, Per Kroll
    
        Requirements: Chris Sibbald (lead), Paul Bramble, Ana Paula Valente Pereira, Leonardo Medeiros, Kurt Sand, Bruce
        MacIsaac, Jim Ruehlin, Ricardo Balduino, and others.
    
        Change management: Chris Sibbald (lead), Kurt Sand, and others.
    
        Development: Brian Lyons (lead), Scott Ambler, Ricardo Balduino, and others.
    
        Architecture: Mark Dickson (lead), Jim Ruehlin, Ana Pereira, Chris Doyle, and others.
    
        Test: Brian Lyons (lead), Nate Oster, Jeff Smith, Dana Spears, and others.
    
        General: Steve Adolph (lead),
    
        Developer outreach: Per Kroll / Naveena Bereny (leads), Ricardo Balduino, Scott Ambler, Kurt Sand, and others.
     
    3 Project Practices and Measurements
    The OpenUP component team will use OpenUP practices adapted to address the fact that we are doing content development
    rather than coding. Key artifacts include: Project Plan (Word), Work Item List (Bugzilla + Excel), Iteration Plan
    (Word), and Status Assessment (Word).
 
    Progress is tracked using two primary measurements using a point system. It is estimated that 1 point represents 2h of
    work:
 
    
        Project backlog: The project backlog shows progress relative to overall work to be done within the project.
    
        Iteration backlog: The iteration backlog shows progress relative to work intended for the current iteration.
     
    4  Project Milestones and Objectives
    This section covers objectives for the entire EPF 1.0 project.
 
    
        Governance process in place, including guidelines for how to work with CVS
    
        Tutorials available to help people adopt EPF composer
    
        Process tools matured and usable to produce a broad set of processes and method content.
    
        Basic set of interfaces / APIs defined, stabilized, and delivered.
    
        Deliver basic printing capability.
    
        Mature content. Deliver a mature OpenUP, and beta quality of one or more other processes, whereof one should be
        another agile process.
    
        Generate a high level of interest around EPF v1.0. Press releases, papers, tutorials, workshops, presentations,
        etc.
    
        Identify a broader set of process champions with an interest to contribute to EPF within a specific domain, such as
        MDA or project management, or a specific vertical such as telecom.
 
    
        
            | Phase | Iteration | Primary Objective (risks and use cases scenarios) | Scheduled start or milestone | Duration Estimate (calendar days) |  
            | Inception/ Warm-up | M0 | 
                    
                        Project acceptance and provisioning.
                    
                        IBM donation. Project environment established.
                    
                        Committer meeting. Project organization and plan agreed to.
                     | 12/23/2005 1/15/2005
 | 24 days |  
            | Elaboration | M1 | 
                    
                        Legal process to be completed by initial committers
                    
                        Train all committers.
                    
                        Provision project, set up website, mailing lists, etc.
                    
                        Agree on structure of OpenUP; agree on how to structure of OpenUP into work units, principles and
                        resources to evolve each unit.
                    
                        Identify outreach activities
                     | 1/16/2006 2/28/2006
 
 | 43 days |  
            | Elaboration | M2 | 
                    
                        Agree on naming conventions
                    
                        Agree to key structural information for OpenUP (e.g. tasks, work products, etc. defined)
                    
                        Engage with additional contributors
                    
                        Agree on user experience and have a few examples for OpenUP
                    
                        Validate extensibility / composibility of OpenUP
                     | 3/1/2006 4/15/2006
 
 | 45 days |  
            | Elaboration | M3 | 
                    
                        Identify an initial set of key promoters presenting at conferences, writing blogs and articles,
                        etc.
                    
                        Agree on general structure of OpenUP
                     | 4/15/2006 5/31/2006
 | 45 days |  
            | Construction | M4 | 
                    
                        Produce realistic plans for M5
                    
                        Agree on a management process
                    
                        Have all structural content decisions taken
                    
                        Have 30% of content ready for review
                    
                        Plan Agile2006, SD Best Practices, and other outreach activities
                     | 6/1/2006 7/16/2006
 
 | 45 days |  
            | Construction | M5 | 
                    
                        Finalize structure
                    
                        Improve usability and first impression
                    
                        Review 30% of content
                    
                        Make additional 30% of content available for review
                    
                        Establish a functioning management process for the project
                    
                        Establish a review board
                    
                        Produce initial draft collateral for EPF 1.0 launch
                    
                        Make preview at Agile 2006 successful
                    
                        Start to build a user community. Identify 2 pilot projects.
                     | 7/17/2006 8/4/2006
 | 21 days |  
            | Construction | M6 | 
                    
                        Improve usability and first impression
                    
                        Have 60% of content reviewed
                    
                        Make the final 40% of content available for review
                    
                        Produce more draft collateral for EPF 1.0 launch
                    
                        Continue building a user community
                     | 8/7/2006 9/1/2006
 | 28 days |  
            | Transition / End Game | M7 | 
                    
                        End game
                    
                        Finalize content 0.9
                    
                        Finalize launch collateral
                    
                        Plan next release
                     | 9/4/2006 9/29/2006
 | 28 days |  
    5 Deployment
    N/A.
 
    6 Lessons Learned
    N/A.
 
 
 
 
 |